Steklarna Hrastnik Glass Container Production Plant, Hrastnik, Slovenia

Email-Icon
 
Print-Icon
 
Link-to-us
key facts
Key Data
Order year
2004
Project type
Glass container production
Location
Hrastnit, Slovenia
Estimated investment
€27 million
Construction started
December 2004
Completion
October 2005
Sponsors
Steklarna Hrastnik

Steklarna Hrastnik, one of the largest producers of glass containers for premium food products in Slovenia, announced in October 2004 that it was to undertake the construction of a special purpose glass container and tableware production plant in the Podkraj industrial zone near Hrastnik in central Slovenia, on the right bank of the Sava river adjacent to the Hrastnik commune.

The new plant required an estimated investment of €27 million and was completed and operational by autumn 2005. The construction process started in December 2004 and was planned to take ten months putting the opening date in October 2005. The new plant is a response to the opening of new markets in the European Union and the United States where the majority of the products will be distributed. The new facility is believed to be of strategic importance for the long-term development of the company.

The plant employs 210 personnel and will has an annual production capacity of 33,000t/yr. The new factory represents one of the largest investments in Slovenia in 2004; the new facility is one of the most modern of its kind in Europe. The facility produces a wide variety of glass containers suitable for the packaging of products such as food (bottled vegetables and sauces), olive oil, perfume, soft drinks, spirits and wine. Containers are produced in a range of sizes for these applications from 40ml up to 1,000ml.

CONSTRUCTION OF THE NEW FACILITY

In October 2004 RUDIS d.d. Trbovlje was awarded the turnkey Engineer, Procure, Construct (EPC) construction contract for the new facility. The contract was for the complete factory including fabrication of the building and construction and installation of the furnaces and glass moulding equipment. RUDIS was involved in the investment from the very beginning when Steklarna Hrastnik started to consider the new facility.

RUDIS started work on the project with Steklarna Hrastnik in spring 2004 on planning the implementation of the project and by producing building permit documentation, and the structural and basic design of the plant. The new plant has been designed staround four furnaces and four production lines.

RUDIS constructed the facility in a standard steel frame, concrete block and aluminium panel design and then supplied and installed all of the mechanical, electrical and pipe services (completed in June 2005). By August 2005 the construction was over and the natural gas furnaces had been built.

RUDIS have also been involved in the installation of several furnace pre-silos, flue gas purification (scrubbers to remove NOx and other environmentally problematic gases), conveyor belts to feed the furnaces with cullet and other raw materials and air-cooling systems (for cooling the product containers).

FURNACES

The new furnaces use oxyfuel firing as this is now widely recognised as the most energy efficient and environmentally friendly process. The oxyfuel furnace reduces a glass manufacturer’s fuel use by 15% to 45%, NOx emissions by 80%, and particulates by 60%. The process also increases productivity by 25%. However, because of higher temperatures and production of alkali vapours, refractories corrode significantly faster in oxyfuel furnaces; furnace crown life can be shortened by a factor of two to three. The four new furnaces at Hrastnik have been installed with a new extended life refractory lining which will also reduce long-term maintenance costs.

PRODUCTION LINES

The furnace produces the molten glass which is then divided into hot-glass melt gobs by dosage devices with special shears, which are then passed into suitable moulds on a moulding machine. The gobs' form, weight, speed and temperature are programmed and depend on the product required. The moulding process (pressed, blown, etc.) is carried out and a hot form of the product is shaped, which then needs to be cooled (using air cooling systems).

Following this, products are reheated later for fire polishing so that the product has smooth surfaces and so that all characteristic traces of automatic production are removed. Each product is then put into a cooling / annealing furnace, to remove tensions in the glass by slow cooling (since initially the temperature is between 900°C to 1,000°C and is quickly reduced to 400°C, which could cause defects). At the end of the cooling furnace products are inspected by quality control and rejects removed.



Expand Image Expand Image
The new glass container and tableware production plant represented one of the largest investments in Slovenia in 2004 and is one of the most modern of its kind in Europe.



Expand Image Expand Image
The facility produces a wide variety of glass containers suitable for the packaging of products such as food (bottled vegetables and sauces), olive oil, perfume, soft drinks, spirits and wine.



Expand Image Expand Image
In October 2004 RUDIS d.d. Trbovlje was awarded the turnkey EPC contract for the new facility.



Expand Image Expand Image
The new plant required an estimated investment of €27 million and was completed and operational by autumn 2005.



Expand Image Expand Image
RUDIS constructed the facility in a standard steel frame, concrete block and aluminium panel design.



Expand Image Expand Image
The new plant has been designed around four furnaces and four production lines.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Home
New On This Site
Products & Services
Company A-Z
Projects
Features
White Papers
Jobs & Careers
News & Updates
Events Listings
Newsletter Archive
Newsletter Sign-Up
Advertise
About Us
Client Area


RSS What is RSS
News, views and contacts from the global packaging industry